Scope of Project: To fire stop and seal-off a vent corridor to accommodate asbestos removal operations. We also installed platform hoardings to house asbestos air handling (negative pressure) units.
Outcome: The project was successfully installed on time and the Sealed fire wall protected the station from potential emissions of asbestos particles during removal operations; critically ensuring no danger to the public during the complex phases of removal operations.
Client: Land Securities
Main contractor: Keltbray Ltd
Project Duration: 6 days
Installation Date: May 2015